A company's vCIO Process

A company's vCIO Process

A company's vCIO Process is its calendar of meetings and audits for the year, built from one of your vCIO Process templates. Open the company's vCIO Process link to assign it, follow it during the year and adjust it for that client.

Assign a process

Click Assign vCIO Process and pick the vCIO Process template. Process Alignment sets the date the template's items are counted from: the client's Fiscal Year, the Calendar Year or a Custom Date. Propel Your MSP creates the current and the next year, then adds a new year as each one ends.

  • Mark past items as cancelled? When you start mid-year, check it so the items whose target date has already passed are marked Cancelled instead of waiting to be scheduled.
  • Company Audit Site Policy chooses which sites the process's audits cover: All sites, Only the primary site, Only the following or All sites except the following. You can change it per audit item later.

Follow the year

Each year lists its items with a status and a button for the next step.

Status Meaning Button
Target Date Not scheduled yet. Schedule a meeting, Start an audit
Scheduled The meeting has a date. It shows Missed when that date is more than 7 days past. Done
Due Date, In Progress The audit is started. Continue
Done The meeting was held, or the audit is finished. View for an audit
Cancelled The item was skipped. none

The 2026 vCIO Process of Bluewater Credit Union with Done, Cancelled, Missed, Target Date and Scheduled items and their next-step buttons.

Schedule sets the meeting's date and can put it in your Outlook calendar: see Schedule meetings and push them to Outlook 365. Done asks for the Actual Date and optional Comments. Start opens the audit, as in Run a company audit. The item shows Done once the audit is finished.

Adjust it for this company

  • Add New Meeting / Audit adds an item for this company only.
  • In an item's … menu, Configure changes its type, its target date or its notification.
  • Mark as Cancelled keeps the item, with a comment on why it was skipped. Delete removes it. A done item can't be deleted.
  • Reset State reopens a cancelled or done item. For an audit, it also unlinks the audit.

When the company already has later years, Propel asks Apply to Future vCIO Processes?. Click Yes, apply to all to make the same change in every later year, or No, just this one.

Notifications

Each item notifies the vCIO, the Account Manager or both, a set number of days before its target date, as set in the template. An item that is done or cancelled sends nothing. Each person gets an email or a PSA activity, as set in Your profile and notifications. The template can also create a service ticket in your PSA. To send a reminder now, open the item's View Details and click Send Notification Now.

Reset the process to its template

To undo this company's changes, click (Change) next to Based on template, pick the same template and save:

  • Items that match the template, by meeting type or questionnaire and target date, get the template's notification settings back.
  • Template items that are missing, including deleted ones, are recreated. Check Mark past items as cancelled? so the past ones don't reopen.
  • Items the template doesn't have are deleted, unless they are started: a meeting with a date or an audit in progress stays.

Done items keep their status and dates.

Related